Sobha One Residences Phase 1 Project Schedule
Sobha One Residences Phase 1 Project Schedule gives the stage-wise construction timeline of Phase 1. The work starts with earthwork and site leveling on 1 June 2026. It then moves to foundation, plinth, basement flooring, RCC structure, masonry, plastering, doors, windows, electrical, plumbing, flooring, painting, fire safety, elevation, and landscaping. The final listed work is internal and external development with landscaping, planned to end on 31 July 2032.
This schedule helps buyers understand how Phase 1 work will move on site. It shows the start and end dates for each major activity. It also shows which works are applicable and which works are not part of the schedule. Since this is a high-rise phase, many works will run side by side for better construction flow.