Sobha One Residences Phase 1 Project Schedule


Featured Image of Phase 1 Project Schedule

Sobha One Residences Phase 1 Project Schedule gives the stage-wise construction timeline of Phase 1. The work starts with earthwork and site leveling on 1 June 2026. It then moves to foundation, plinth, basement flooring, RCC structure, masonry, plastering, doors, windows, electrical, plumbing, flooring, painting, fire safety, elevation, and landscaping. The final listed work is internal and external development with landscaping, planned to end on 31 July 2032.

This schedule helps buyers understand how Phase 1 work will move on site. It shows the start and end dates for each major activity. It also shows which works are applicable and which works are not part of the schedule. Since this is a high-rise phase, many works will run side by side for better construction flow.

Sobha One Residences Phase 1 Schedule Overview


The project schedule of Sobha One Residences Phase 1 is split into three main parts. These are sub-structure work, super-structure work, and finishing work.

Sub-structure work covers the early site and basement work. Super-structure work covers the main tower frame and wall work. Finishing work covers the final usable parts of the building, such as painting, fire safety, elevation, and landscaping.

The Phase 1 schedule starts on 1 June 2026 and runs up to 31 July 2032. This gives buyers a clear idea of the full construction period.

Sub-Structure Schedule of Sobha One Residences Phase 1


Sub-structure work is the first stage in the Sobha One Residences Phase 1 Project Schedule. It includes earthwork, foundation, plinth, and parking floor work.

Project Work Applicable Start Date End Date
Earth work and leveling preparation Yes 1 June 2026 26 February 2027
Foundation footing work Yes 16 July 2026 27 April 2027
Up to plinth level Yes 16 July 2026 27 April 2027
Parking floor work below ground level Yes 14 September 2026 24 October 2027
Retaining wall work No

The first work on site is earthwork and leveling. It is planned from 1 June 2026 to 26 February 2027. This stage prepares the land for the next construction steps.

Foundation footing work and also the plinth work are planned from 16 July 2026 to 27 April 2027. These works form the base of the tower. Parking floor work below ground level starts on 14 September 2026 and ends on 24 October 2027.

Retaining wall work is marked as not applicable for this Phase 1 schedule.

Super-Structure Schedule of Sobha One Residences Phase 1


Super-structure work is the main tower-building stage. It starts after the early foundation work begins.

Project Work Applicable Start Date End Date
RCC or MS framed structure Yes 11 February 2027 13 October 2029
Masonry construction Yes 8 December 2027 11 January 2030
Inside, outside and ceiling plastering Yes 7 January 2028 11 April 2030
Doors, windows and ventilators Yes 21 February 2028 10 July 2030
Basic water, sanitary and electrical work Yes 21 April 2028 8 October 2030
Dadoing, skirting, flooring and tile work Yes 5 June 2028 6 January 2031
Railing and grill fixing Yes 22 December 2028 6 April 2031

The RCC or MS framed structure is planned from 11 February 2027 to 13 October 2029. This is one of the main parts of the schedule because it forms the tower frame.

Masonry work starts on 8 December 2027 and goes up to 11 January 2030. Plastering starts from 7 January 2028, while doors, windows, and ventilator work starts from 21 February 2028.

Basic water supply, sanitary, and electrical work starts on 21 April 2028. Flooring and tile work starts on 5 June 2028. Railing and grill fixing starts later, from 22 December 2028.

Finishing Works Schedule of Sobha One Residences Phase 1


Finishing work gives the building its final look and usable condition. This stage starts while some internal works are still moving.

Project Work Applicable Start Date End Date
Electrical, water supply and sanitary finishing Yes 21 January 2029 5 July 2031
Painting Yes 7 March 2029 3 October 2031
Fire safety fittings and network Yes 6 April 2029 2 December 2032
Weatherproofing work Yes 6 May 2029 31 January 2032
Wardrobe, showcase, kitchen cabinet and puja work No
Elevation work Yes 20 June 2029 31 March 2032
Internal, external and landscape works Yes 4 August 2029 31 July 2032

Electrical, water supply, and sanitary finishing starts on 21 January 2029. Painting starts on 7 March 2029 and is planned to continue until 3 October 2031.

Fire safety fitting and network work starts on 6 April 2029. This work is planned up to 2 December 2032. Weatherproofing starts on 6 May 2029 and ends on 31 January 2032.

Elevation work starts on 20 June 2029 and ends on 31 March 2032. Internal, external, and landscape works start on 4 August 2029 and are planned to end on 31 July 2032.

Wardrobe, showcase, kitchen cabinet, and puja work are marked as not applicable in this schedule.

Key Dates in Sobha One Residences Phase 1 Project Schedule


Here are the main dates buyers should know:

  • Earthwork iss going to starts on 1 June 2026
  • Foundation work starts on 16 July 2026
  • Parking floor work starts on 14 September 2026
  • RCC structure work starts on 11 February 2027
  • Masonry work will get starts on 8 December 2027
  • Water, sanitary and electrical basic work starts on 21 April 2028
  • Finishing work starts on 21 January 2029
  • Painting works are starts on 7 March 2029
  • Fire safety work will starts on 6 April 2029
  • Elevation work starts on 20 June 2029
  • Landscaping and external works end on 31 July 2032

These dates show that the work is planned in stages. Some activities also overlap, which is normal in large high-rise projects.

What This Schedule Means for Buyers


The Sobha One Residences Phase 1 Project Schedule helps buyers track the work in a simple way. It does not show only one final date. It shows how the work is planned from the ground stage to the final landscape stage.

Buyers can use this schedule to understand when the foundation work starts, when the tower frame begins, and when finishing works are planned. It also helps them know that Phase 1 has a long construction cycle, with work running from 2026 to 2032.

This page covers only the Phase 1 project schedule. Buyers should not mix it with other phases, because each phase can have a different work plan and timeline.

Sobha Limited Prelaunch Project is Sobha One World.

FAQs


1. What is the start date of Sobha One Residences Phase 1 Project Schedule?

Sobha One Residences Phase 1 Project Schedule starts on 1 June 2026 with earthwork and site leveling.

2. When does foundation work start in Sobha One Residences Phase 1?

Foundation footing work starts on 16 July 2026 and is planned to end on 27 April 2027.

3. When does RCC structure work start in Phase 1?

RCC or MS framed structure work starts on 11 February 2027 and ends on 13 October 2029.

4. When does painting work start in Sobha One Residences Phase 1?

Painting work starts on 7 March 2029 and is planned to end on 3 October 2031.

5. When does fire safety work start in Phase 1?

Fire safety fitting and network work starts on 6 April 2029 and ends on 2 December 2032.

6. When is the final listed work expected to end?

The final listed work is internal, external, and landscape work. It is planned to end on 31 July 2032.

7. Is retaining wall work part of the Phase 1 schedule?

No, retaining wall work is marked as not applicable in the Phase 1 schedule.

8. Is kitchen cabinet or wardrobe work included in this schedule?

No, wardrobe, showcase, kitchen cabinet, and puja work are marked as not applicable.