Sobha One Residences Phase 2 Project Schedule


Featured Image of Phase 2 Project Schedule

Sobha One Residences Phase 2 Project Schedule gives the full construction plan of Phase 2, starting from 18 August 2026 and going up to 30 November 2032. The first work is earthwork and site leveling. After that, the schedule moves into foundation, plinth, basement parking floors, RCC frame, masonry, plastering, doors, windows, electrical lines, plumbing lines, flooring, painting, fire safety, elevation, and landscape work.

This page is useful for buyers who want to understand the real work flow of Phase 2. It shows when the base work starts, when the tower structure begins, and when the finishing and outside works are planned. Since this is a high-rise phase, many activities are planned to run together during the construction period.

Sobha One Residences Phase 2 Schedule Overview


The Phase 2 schedule is divided into three main work parts. These are sub-structure, super-structure, and finishing works.

Sub-structure work covers the starting stage of the project. It includes land preparation, foundation, plinth, and parking floor work below ground level.

Super-structure work starts once the base work is ready. This part includes RCC frame, masonry, plastering, doors, windows, basic water supply, sanitary work, electrical work, flooring, railings, and grills.

Finishing works come later. These include painting, fire safety, weatherproofing, elevation, and internal and external landscape work.

Sub-Structure Schedule of Sobha One Residences Phase 2


Sub-structure work is the first part of the Sobha One Residences Phase 2 Project Schedule. This stage prepares the land and creates the base for the tower work.

Project Work Applicable Start Date End Date
Earth work and leveling preparation Yes 18 August 2026 15 May 2027
Foundation footing work Yes 2 October 2026 14 July 2027
Up to plinth level Yes 2 October 2026 14 July 2027
Parking floor work below ground level Yes 1 December 2026 10 January 2028
Retaining wall work No

Earthwork and leveling are planned from 18 August 2026 to 15 May 2027. This is the first ground activity before the main foundation work moves ahead.

Foundation footing work starts on 2 October 2026 and ends on 14 July 2027. The work up to plinth level follows the same timeline.

Parking floor work below ground level starts on 1 December 2026 and continues until 10 January 2028. Retaining wall work is not included in the Phase 2 schedule.

Super-Structure Schedule of Sobha One Residences Phase 2


Super-structure work is the part where the tower starts coming up above the base level. It is one of the longest parts of the Phase 2 schedule.

Project Work Applicable Start Date End Date
RCC or MS framed structure Yes 30 April 2027 30 December 2029
Masonry construction Yes 24 February 2028 30 March 2030
Inside, outside and ceiling plastering Yes 25 March 2028 28 June 2030
Doors, windows and ventilators Yes 9 May 2028 26 September 2030
Basic water, sanitary and electrical work Yes 8 July 2028 25 December 2030
Dadoing, skirting, flooring and tile work Yes 22 August 2028 25 March 2031
Railing and grill fixing Yes 10 March 2029 23 June 2031

The RCC or MS framed structure starts on 30 April 2027 and runs until 30 December 2029. This is the main tower frame work.

Masonry construction begins on 24 February 2028 and continues until 30 March 2030. Plastering starts on 25 March 2028 and goes on until 28 June 2030.

Doors, windows, and ventilator work start on 9 May 2028. Basic water supply, sanitary, and electrical work starts on 8 July 2028.

Flooring, dadoing, skirting, and tile work start from 22 August 2028. Railing and grill fixing starts on 10 March 2029 and is planned to end on 23 June 2031.

Finishing Works Schedule of Sobha One Residences Phase 2


Finishing work comes after the main tower work starts moving well. This stage gives the building its final look and also covers safety and external works.

Project Work Applicable Start Date End Date
Electrical, water supply and sanitary finishing Yes 9 April 2029 21 September 2031
Painting Yes 24 May 2029 20 December 2031
Fire safety fittings and network Yes 23 June 2029 19 March 2032
Weatherproofing work Yes 23 July 2029 17 June 2032
Wardrobe, showcase, kitchen cabinet and puja work No
Elevation work Yes 6 September 2029 16 August 2032
Internal, external and landscape works Yes 21 October 2029 30 November 2032

Electrical, water supply, and sanitary finishing starts on 9 April 2029 and ends on 21 September 2031. Painting begins on 24 May 2029 and is planned up to 20 December 2031.

Fire safety fitting and network work starts on 23 June 2029. It is planned to continue until 19 March 2032. Weatherproofing work starts on 23 July 2029 and ends on 17 June 2032.

Elevation work starts on 6 September 2029 and ends on 16 August 2032. The last listed work is internal, external, and landscape work. It starts on 21 October 2029 and ends on 30 November 2032.

Wardrobe, showcase, kitchen cabinet, and puja work are not part of this schedule.

Main Dates Buyers Should Know


Sobha One Residences Phase 2 starts with land-level work in August 2026. Foundation work begins in October 2026, and basement parking floor work begins in December 2026.

The main RCC frame starts on 30 April 2027. Masonry work begins in February 2028, followed by plastering, doors, windows, electrical, plumbing, and flooring work during 2028.

Finishing works here will begin in April 2029 with electrical, water supply, and sanitary finishing. Painting starts in May 2029, fire safety work starts in June 2029, and elevation work starts in September 2029.

The final listed activity is internal, external, and landscape work. It is planned to end on 30 November 2032.

What This Schedule Means for Buyers


The Sobha One Residences Phase 2 Project Schedule helps buyers read the construction plan in a clear way. It shows the full path from land preparation to final landscape work.

This is also useful because the schedule does not depend on only one final date. Buyers can check each work stage separately and understand how the phase is expected to move over the years.

This page covers only the Phase 2 project schedule. Other phases may have different dates, work flow, and completion timelines.

Sobha Limited Prelaunch Project is Sobha One World.

FAQs


1. What is the start date of Sobha One Residences Phase 2 Project Schedule?

Sobha One Residences Phase 2 Project is Scheduled on 18 August 2026 with earthwork and site leveling.

2. When does foundation work start in Sobha One Residences Phase 2?

Foundation footing work starts on 2 October 2026 and ends on 14 July 2027.

3. When does RCC structure work start in Phase 2?

RCC or MS framed structure work starts on 30 April 2027 and ends on 30 December 2029.

4. When does masonry work start in Phase 2?

Masonry construction will get starts on 24 February 2028 and ends on 30 March 2030.

5. When does painting work start in Sobha One Residences Phase 2?

Painting work starts on 24 May 2029 and ends on 20 December 2031.