Sobha One Residences Phase 3 Project Schedule


Featured Image of Phase 3 Project Schedule

Sobha One Residences Phase 3 Project Schedule gives the full construction timeline of Phase 3 from 1 October 2026 to 30 September 2033. The schedule starts with earthwork and site leveling, then moves into foundation, plinth, basement parking floor work, RCC frame, masonry, plastering, doors, windows, electrical lines, plumbing, flooring, painting, fire safety, elevation, and landscape work.

This page is focused only on the Phase 3 project schedule. It helps buyers see how the work is planned from the ground stage to the final external works. The schedule also shows that Phase 3 has a longer work window than the earlier phases, with the last listed activity planned for 30 September 2033.

Sobha One Residences Phase 3 Schedule Overview


The Phase 3 schedule is divided into three parts: sub-structure, super-structure, and finishing works.

Sub-structure work covers the early ground work, including earthwork, foundation, plinth, and parking floor work below ground level. This is the base stage of the project.

Super-structure work is where the tower frame and walls come up. It includes RCC or MS frame work, masonry, plastering, doors, windows, basic electrical, water, sanitary, flooring, railings, and grills.

Finishing works come later and cover painting, fire safety, weatherproofing, elevation, and internal and external landscape work. These works give the phase its final usable form.

Sub-Structure Schedule of Sobha One Residences Phase 3


The sub-structure schedule start with earthwork on 1 October 2026. The base-related work then continues through foundation, plinth, and basement parking floor activity.

Project Work Applicable Start Date End Date
Earth work and leveling preparation Yes 1 October 2026 23 April 2028
Foundation footing work Yes 15 November 2026 22 June 2028
Up to plinth level Yes 15 November 2026 22 June 2028
Parking floor work below ground level Yes 14 January 2027 19 December 2028
Retaining wall work No

Earthwork and leveling run from October 2026 to April 2028. This is the starting point of the Phase 3 site work.

The foundation and plinth work are planned in the same window, from 15 November 2026 to 22 June 2028. This keeps the main base work aligned before the tower frame moves ahead.

Basement parking floor work starts in January 2027 and continues until December 2028. Retaining wall work is not included in this Phase 3 schedule.

Super-Structure Schedule of Sobha One Residences Phase 3


The super-structure stage is the main tower-building part of the schedule. It begins with the RCC or MS frame and then moves into wall work, plastering, joinery, services, flooring, railings, and grills.

Project Work Applicable Start Date End Date
RCC or MS framed structure Yes 13 June 2027 28 April 2031
Masonry construction Yes 8 April 2028 27 July 2031
Inside, outside and ceiling plastering Yes 8 May 2028 25 October 2031
Doors, windows and ventilators Yes 22 June 2028 24 December 2031
Basic water, sanitary and electrical work Yes 21 August 2028 7 February 2032
Dadoing, skirting, flooring and tile work Yes 5 October 2028 23 March 2032
Railing and grill fixing Yes 23 April 2029 22 May 2032

The RCC or MS framed structure is planned from 13 June 2027 to 28 April 2031. This is the main tower frame and one of the longest parts of the Phase 3 schedule.

Masonry begins in April 2028, followed by plastering in May 2028. Doors, windows, and ventilator work come in from June 2028.

Basic water supply, sanitary, and electrical work are planned from August 2028. Flooring, dadoing, skirting, and tile work follow from October 2028. Railing and grill fixing move in later, from April 2029.

Finishing Works Schedule of Sobha One Residences Phase 3


Finishing work gives the towers their final look and usable condition. This stage also includes safety, weather protection, elevation, and outside development.

Project Work Applicable Start Date End Date
Electrical, water supply and sanitary finishing Yes 23 May 2029 20 August 2032
Painting Yes 7 July 2029 18 December 2032
Fire safety fittings and network Yes 6 August 2029 3 January 2033
Weatherproofing work Yes 5 September 2029 19 March 2033
Wardrobe, showcase, kitchen cabinet and puja work No
Elevation work Yes 20 October 2029 17 June 2033
Internal, external and landscape works Yes 4 December 2029 30 September 2033

The finishing stage begins in May 2029 with electrical, water supply, and sanitary finishing. Painting starts in July 2029, while fire safety work begins in August 2029.

Weatherproofing is planned from September 2029, followed by elevation work from October 2029. The final listed activity is internal, external, and landscape work, which runs up to 30 September 2033.

Wardrobe, showcase, kitchen cabinet, and puja work are not part of this project schedule.

Main Dates in Sobha One Residences Phase 3 Project Schedule


Sobha One Residences Phase 3 starts with earthwork on 1 October 2026. Foundation work begins on 15 November 2026, and basement parking floor work starts on 14 January 2027.

The main tower frame starts on 13 June 2027. Masonry, plastering, doors, windows, services, and flooring enter the schedule during 2028.

Finishing works begin in May 2029. Painting, fire safety, weatherproofing, elevation, and landscape work continue in later stages. The last listed work closes on 30 September 2033.

What Buyers Can Understand From This Schedule


The Sobha One Residences Phase 3 Project Schedule gives buyers a clear idea of how this phase is planned over the years. It does not depend on one final date alone. It shows the work flow from land preparation to final landscaping.

The schedule also helps buyers understand why high-rise projects take time. The main structure, services, and finishing works overlap across different years, which is normal for a large tower phase.

This page should be read only for Phase 3. Other phases may have different dates, different work stages, and different completion windows.

Sobha Limited Prelaunch Project is Sobha One World.

FAQs


1. What is the start date of Sobha One Residences Phase 3 Project Schedule?

Sobha One Residences Phase 3 of Project Schedule will starts on 1 October 2026 with earthwork and leveling preparation.

2. When does foundation work start in Sobha One Residences Phase 3?

Foundation footing work here starts on 15 November 2026 and ends on 22 June 2028.

3. When does RCC structure work start in Phase 3?

RCC or MS framed structure work starts on 13 June 2027 and ends on 28 April 2031.