Sobha One Residences Phase 4 Project Schedule


Featured Image of Phase 4 Project Schedule

Sobha One Residences Phase 4 Project Schedule gives the full work timeline for ONE RESIDENCES AT SOBHA ONE WORLD Ph4 W7 and 8. The schedule starts on 1 October 2026 with earthwork and site leveling. It ends on 30 September 2033 with internal, external, and landscape works. The main work stages include foundation, plinth, basement floor work, RCC structure, masonry, plastering, doors, windows, electrical, plumbing, flooring, painting, fire safety, elevation, and landscaping.

This page covers only the Phase 4 project schedule. It helps buyers check how the construction work is planned from the ground stage to the final finishing stage.

Sobha One Residences Phase 4 Schedule Overview


The Phase 4 schedule is divided into three parts.

The first part is sub-structure work. This covers earthwork, foundation, plinth, and basement parking floor work.

The second part is super-structure work. This covers RCC frame, masonry, plastering, doors, windows, services, tiles, railings, and grills.

The last part is finishing work. This includes painting, fire safety, weatherproofing, elevation, and landscaping.

Sub-Structure Schedule


Project Work Status Start Date End Date
Earth work and leveling preparation Yes 1 October 2026 23 April 2028
Foundation footing work Yes 15 November 2026 22 June 2028
Up to plinth level Yes 15 November 2026 22 June 2028
Parking floor work below ground level Yes 14 January 2027 19 December 2028
Retaining wall work No

Earthwork starts first on 1 October 2026. This prepares the site for the main base work.

Foundation and plinth work start on 15 November 2026. Both are planned to close by 22 June 2028.

Basement parking floor work starts on 14 January 2027 and runs up to 19 December 2028. Retaining wall work is not listed for Phase 4.

Super-Structure Schedule


Project Work Status Start Date End Date
RCC or MS framed structure Yes 13 June 2027 28 April 2031
Masonry construction Yes 8 April 2028 27 July 2031
Inside, outside and ceiling plastering Yes 8 May 2028 25 October 2031
Doors, windows and ventilators Yes 22 June 2028 24 December 2031
Basic water, sanitary and electrical work Yes 21 August 2028 7 February 2032
Dadoing, skirting, flooring and tile work Yes 5 October 2028 23 March 2032
Railing and grill fixing Yes 23 April 2029 22 May 2032

The RCC or MS frame starts on 13 June 2027. This is the main tower structure work and runs until 28 April 2031.

Masonry starts in April 2028. Plastering starts one month later, in May 2028.

Doors and windows start from 22 June 2028. Basic water, sanitary, and electrical work starts from 21 August 2028.

Tile, skirting, and flooring work starts from 5 October 2028. Railing and grill fixing starts from 23 April 2029.

Finishing Works Schedule


Project Work Status Start Date End Date
Electrical, water supply and sanitary finishing Yes 23 May 2029 20 August 2032
Painting Yes 7 July 2029 18 December 2032
Fire safety fittings and network Yes 6 August 2029 3 January 2033
Weatherproofing work Yes 5 September 2029 19 March 2033
Elevation work Yes 20 October 2029 17 June 2033
Internal, external and landscape works Yes 4 December 2029 30 September 2033
Wardrobe, showcase, kitchen cabinet and puja work No

Finishing work begins from 23 May 2029 with electrical, water supply, and sanitary finishing.

Painting starts on 7 July 2029. Fire safety work starts on 6 August 2029. Weatherproofing starts on 5 September 2029.

Elevation work begins on 20 October 2029. The last listed work is internal, external, and landscape work. It ends on 30 September 2033.

Wardrobe, showcase, kitchen cabinet, and puja work are not part of this schedule.

Main Dates in Sobha One Residences Phase 4 Project Schedule


Sobha One Residences Phase 4 starts with earthwork on 1 October 2026. Foundation work begins on 15 November 2026.

Basement floor work starts on 14 January 2027. The RCC frame begins on 13 June 2027.

Main wall work, plastering, doors, windows, plumbing, electrical work, and flooring move through 2028 to 2032.

Finishing works begin in May 2029. The final listed work ends on 30 September 2033.

What This Schedule Means for Buyers


Sobha One Residences Phase 4 Project Schedule gives buyers a clear view of the construction flow. It shows when the base work starts, when the tower frame begins, and when finishing works are planned.

The schedule also shows that many works overlap. This is common in large high-rise projects.

This page is only for Phase 4. Other Sobha One Residences phases may have different dates and work timelines.

FAQs


1. What is the start date of Sobha One Residences Phase 4 Project Schedule?

Sobha One Residences Phase 4 Project Schedule is starting on 1 October 2026.

2. When does foundation work start in Phase 4?

Foundation footing work starts on 15 November 2026 and ends on 22 June 2028.

3. When does RCC work start in Sobha One Residences Phase 4?

RCC or MS framed structure work starts on 13 June 2027 and ends on 28 April 2031.

4. When does finishing work start in Phase 4?

Finishing work starts from the 23 May 2029 with electrical, water supply, and sanitary finishing.

5. When does painting work start in Phase 4?

Painting work starts on 7 July 2029 and ends on 18 December 2032.

6. When does fire safety work start in Phase 4?

Fire safety fitting and network work starts on 6 August 2029 and ends on 3 January 2033.