Sobha One Residences Phase 5 Project Schedule


Featured Image of Phase 5 Project Schedule

Sobha One Residences Phase 5 Project Schedule gives the construction timeline for ONE RESIDENCES AT SOBHA ONE WORLD Ph5 W9,10,11. The work begins on 18 August 2026 with earthwork and land leveling. The final listed activity is internal, external, and landscape work, planned up to 28 February 2033.

This phase moves in three main steps. First comes the base work. Then the tower structure and wall work move ahead. After that, the project enters finishing, fire safety, elevation, and landscape work.

Phase 5 Schedule Overview


Work Stage Main Work Covered Timeline
Sub-Structure Earthwork, foundation, plinth, basement floor August 2026 to January 2028
Super-Structure RCC frame, masonry, plastering, services, flooring April 2027 to September 2031
Finishing Works Painting, fire safety, weatherproofing, elevation, landscaping April 2029 to February 2033

Phase 5 has a long work window because many activities overlap. This is common in large apartment towers. Base work, tower work, and finishing work do not wait fully for one stage to close before the next stage begins.

Sub-Structure Schedule


Project Work Start Date End Date
Earth work and leveling preparation 18 August 2026 15 May 2027
Foundation footing work 2 October 2026 14 July 2027
Up to plinth level 2 October 2026 14 July 2027
Parking floor work below ground level 1 December 2026 10 January 2028
Retaining wall work Not applicable

The first site work begins with earthwork in August 2026. Foundation and plinth work follow in October 2026, keeping the base work on the same line.

The basement parking floor work has a longer window. It runs from December 2026 to January 2028. Retaining wall work is not part of this Phase 5 schedule.

Super-Structure Schedule


Project Work Start Date End Date
RCC or MS framed structure 30 April 2027 30 March 2030
Masonry construction 24 February 2028 28 June 2030
Inside, outside and ceiling plastering 25 March 2028 26 September 2030
Doors, windows and ventilators 9 May 2028 25 December 2030
Basic water, sanitary and electrical work 8 July 2028 25 March 2031
Dadoing, skirting, flooring and tile work 22 August 2028 23 June 2031
Railing and grill fixing 10 March 2029 21 September 2031

The main tower frame begins in April 2027 and continues until March 2030. This is the key structure work for Phase 5.

Wall work, plastering, doors, windows, service lines, and flooring enter the schedule during from 2028. Railing and grill fixing come later, from March 2029.

Finishing Works Schedule


Project Work Start Date End Date
Electrical, water supply and sanitary finishing 9 April 2029 20 December 2031
Painting 24 May 2029 19 March 2032
Fire safety fittings and network 23 June 2029 17 June 2032
Weatherproofing work 23 July 2029 15 September 2032
Elevation work 6 September 2029 14 November 2032
Internal, external and landscape works 21 October 2029 28 February 2033
Wardrobe, showcase, kitchen cabinet and puja work Not applicable

Finishing work begins in April 2029. Painting, fire safety, weatherproofing, and elevation work all start in the same year.

Important Dates in Phase 5


Sobha One Residences Phase 5 starts with land preparation from the date 18 August 2026. Foundation work begins on 2 October 2026.

The RCC frame starts on 30 April 2027. Masonry, plastering, doors, windows, services, and flooring move into the schedule during 2028.

Finishing works start from 9 April 2029. The final listed work ends on 28 February 2033.

What This Schedule Means


Sobha One Residences Phase 5 Project Schedule shows how the project is planned from ground work to final landscape work. It gives a clear view of each major construction stage without mixing it with other phases.

This page should be read only for Phase 5. Other Sobha One Residences phases may have different start dates, work stages, and completion timelines.

FAQs


1. When does Sobha One Residences Phase 5 Project Schedule start?

Sobha One Residences Phase 5 Project Schedule starts on 18 August 2026.

2. When does foundation work begin in Phase 5?

Foundation work begins on 2 October 2026 and is planned up to 14 July 2027.

3. When does RCC work begin in Phase 5?

RCC or MS framed structure work begins on 30 April 2027 and runs up to 30 March 2030.

4. When does finishing work begin in Phase 5?

Finishing work begins on 9 April 2029 with electrical, water supply, and sanitary finishing.