Sobha One Residences Phase 5 Project Schedule
Sobha One Residences Phase 5 Project Schedule gives the construction timeline for ONE RESIDENCES AT SOBHA ONE WORLD Ph5 W9,10,11. The work begins on 18 August 2026 with earthwork and land leveling. The final listed activity is internal, external, and landscape work, planned up to 28 February 2033.
This phase moves in three main steps. First comes the base work. Then the tower structure and wall work move ahead. After that, the project enters finishing, fire safety, elevation, and landscape work.