Sobha One Residences Phase 6 Project Schedule


Featured Image of Phase 6 Project Schedule

Sobha One Residences Phase 6 Project Schedule shows the entire construction timeline of this phase. The work will start on 1 June 2026 with earthwork and site leveling. The final listed work is internal, external, and landscape development, planned up to 31 August 2032. The schedule covers foundation, plinth, basement floor work, RCC frame, masonry, plastering, doors, windows, electrical, plumbing, flooring, painting, fire safety, elevation, and landscaping.

This page is only for Sobha One Residences Phase 6 Project Schedule. It helps buyers see how the work moves from the first site activity to the final finishing stage.

Sobha One Residences Phase 6 Schedule Overview


Work Stage Main Work Covered Timeline
Sub-Structure Earthwork, foundation, plinth, basement floor June 2026 to October 2027
Super-Structure RCC frame, masonry, plastering, services, flooring February 2027 to April 2031
Finishing Works Painting, fire safety, weatherproofing, elevation, landscaping January 2029 to August 2032

Phase 6 has many works running across the same years. This is normal for a large apartment phase. Base work, tower work, and finishing work move step by step, but some stages also overlap.

Sub-Structure Schedule


Project Work Start Date End Date
Earth work and leveling preparation 1 June 2026 26 February 2027
Foundation footing work 16 July 2026 27 April 2027
Up to plinth level 16 July 2026 27 April 2027
Parking floor work below ground level 14 September 2026 24 October 2027
Retaining wall work Not applicable

Earthwork begins in June 2026. This is the first site activity before the base work moves deeper.

Foundation and plinth work are planned in the same period, from July 2026 to April 2027. Basement parking floor work has a longer window and continues until October 2027.

Retaining wall work is not part of the Phase 6 schedule.

Super-Structure Schedule


Project Work Start Date End Date
RCC or MS framed structure 11 February 2027 13 October 2029
Masonry construction 8 December 2027 11 January 2030
Inside, outside and ceiling plastering 7 January 2028 11 April 2030
Doors, windows and ventilators 21 February 2028 10 July 2030
Basic water, sanitary and electrical work 21 April 2028 8 October 2030
Dadoing, skirting, flooring and tile work 5 June 2028 6 January 2031
Railing and grill fixing 22 December 2028 6 April 2031

The main tower frame begins in February 2027 and continues till October 2029. This is the core structure work of Phase 6.

Masonry starts towards the end of 2027. Plastering, doors, windows, basic services, and flooring move into the schedule during 2028.

Railing and grill fixing begin in December 2028. By this stage, the tower work starts moving into more detailed internal and safety-related work.

Finishing Works Schedule


Project Work Start Date End Date
Electrical, water supply and sanitary finishing 21 January 2029 5 July 2031
Painting 7 March 2029 3 October 2031
Fire safety fittings and network 6 April 2029 1 January 2032
Weatherproofing work 6 May 2029 1 March 2032
Elevation work 20 June 2029 30 April 2032
Internal, external and landscape works 4 August 2029 31 August 2032
Wardrobe, showcase, kitchen cabinet and puja work Not applicable

Finishing work begins in January 2029 with electrical, water supply, and sanitary finishing.

Painting, fire safety, weatherproofing, and elevation work all start in 2029. These works continue into 2031 and 2032.

The final listed activity is internal, external, and landscape work. It is planned from August 2029 to 31 August 2032.

Wardrobe, showcase, kitchen cabinet, and puja work are not included in this schedule.

Important Dates in Phase 6


Sobha One Residences Phase 6 starts with earthwork on 1 June 2026. Foundation work begins on 16 July 2026.

The RCC frame starts on 11 February 2027. Masonry work comes in from 8 December 2027.

Finishing works begin on 21 January 2029. The final listed work ends on 31 August 2032.

What This Schedule Shows


Sobha One Residences Phase 6 Project Schedule gives a clear view of how this phase is planned. It starts with land preparation, then moves into foundation and tower work. Later, the phase shifts into finishing, safety, elevation, and landscaping.

This page should be read only for Phase 6. Other Sobha One Residences phases may have different dates and work timelines.

Sobha Limited Prelaunch Project is Sobha One World.

FAQs


1. When does Sobha One Residences Phase 6 Project Schedule start?

Sobha One Residences Phase 6 Project Schedule starts on 1 June 2026.

2. When does foundation work begin in Phase 6?

Foundation work begins on 16 July 2026 and is planned up to 27 April 2027.

3. When does RCC work begin in Phase 6?

RCC or MS framed structure work begins on 11 February 2027 and runs up to 13 October 2029.

4. When does finishing work begin in Phase 6?

Finishing work begins from 21 January 2029 with electrical, water supply, and sanitary finishing.

5. When does painting work happen in Phase 6?

Painting work is planned from the 7 March 2029 to 3 October 2031.

6. When does the final listed work end?

The final listed work ends on 31 August 2032.

7. Is kitchen cabinet work included in Phase 6 schedule?

No, wardrobe, showcase, kitchen cabinet, and puja work are not included in this schedule.